Week of July 28, 2019:
Week 76 -
As we enter into the 76th week of construction, we can look forward to the following:
Phase 1
Continue to maintain sediment erosion control around the perimeter of the construction site.
A/E Punch List; Section C & D
Install Stage Flooring in Auditorium
Install Auditorium Equipment
Paint: Section A & B & C & D
Test Fire Alarm Devices
Install Access Control
Maintain Landscaping
Rooftop Unit Commissioning
Furniture Deliveries
Equipment Deliveries
Install Telephones
Install Classroom A/V
Noise level: Landscaping and Heavy Equipment Operators
Phase 2 Began June 24, 2019
Continue to maintain sediment erosion control around the perimeter of the construction site.
Remove Bituminous Roads
Demolition Process in Zone 1
Demolition Process in Zone 2
Demolition Process in Zone 3
Install Light Pole Bases
Temporary Construction Fence Installation
Tree Protection
Tree/Brush Removal
Noise level: Heavy Equipment Operators
BMS Eagle in our front foyer area!
Art classroom looking amazing!
Science classroom with lab tables in place! (we can see the old building through the windows!)
Media center shelves in place. Ready for books!